|
Civil
Engineering
Making
the Grade
One of the great things about
garden railways is that you are actually forging a railway line
through the land. Your baseboard is your garden and you have to
build within the constraints of the land you have. When you come
to plan your railway you often find that what looks like a
relatively level piece of land is full of all sorts of
interesting and previously unnoticed undulations. Another
interesting aspect of garden railways is the way they tend to
evolve over time, generally starting small and then growing as
new ideas come along, experience is gained and finances allow.
This has certainly been the case for my line.
My railway started as a dumbbell
shape single track mainline and later a branch line was added.
The branch line was designed to take nothing more than a loco
and two coaches and followed the natural contours of the garden.
This included a short, fairly steep slope of somewhere around 1
in 12 but was not a problem due to the light loads. The
following year saw a major extension and what was the branch
line became main line catering for much heavier trains. Although
the slope caused fewer problems than might have been expected I
decided that this year’s Spring project would be to create a
more even climb and at the same time add a few storage loops in
the same place. The questions were – how steep would I have to
make the gradient and how do you engineer a constant slope
anyway.
The first task was to survey the
land. I know nothing about surveying and had no equipment so a
little improvisation was required. I did have a spirit level and
a laser pointer and I realised that if I blue tacked them
together I could create a means of checking levels over a long
distance.

I held the spirit level where the
slope was going to start, ensuring it was level and pointed the
laser at the base of a box located where the slope was going to
finish. I then marked the position of the top of the spirit
level on a stick which I had put in the ground at the start of
the slope. I now knew the distance I had to climb and the length
I had for the climb. This worked out at 22 centimetres climb
over 6.5 metres – pretty much bang on 1 in 30 which I reckoned
was quite acceptable for my railway.
So I knew how steep I wanted the
slope to be but I then had to work out how to create this
constant slope. At the top and the bottom the current slope was
too shallow and in the middle it was too steep.

At first my plan was to create a
concrete base for the track but then I realised that other work
around the house had left me with some spare 2ft by 2ft paving
slabs – just the right width to support four tracks side by
side. In approximate terms (and most of my work on the railway
is very approximate) these slabs were 60cm long so in order to
create a consistent 1 in 30 slope each slab would have to drop
by 2 cm. A piece of wood was cut up to create little platform
which was 2 cm high and my spirit level was marked 60cm from one
end. Now the job became easy. Starting from the top I dug deep
enough and wide enough for a paving slab and then checked the
slope by resting the spirit level on the ground at one end and
the little wooden platform at the 60cm marker on the spirit
level. The slab was then dropped in place with a bit of sand
underneath and the gradient of the slab checked again with the
spirit level and 2cm high piece of wood. The earth removed was
shoved further down the bank where it was used for filling.

The photo above shows the loops
in place but work on tidying the edge is only half complete.
The storage loops do not run the
whole length of the slope and so there are some points and then
the lower part is single track. The track base becomes narrower
as the points reduce the tracks from four to one. Here I created
a traditional cement base shaped to fit and still on the 1 in 30
gradient. For the single track section slabs would have been too
wide so here I used a different technique. Firstly I laid the
track on the ground where I wanted it to go. I then cut some
garden weed protection layer into a strip just a little wider
than the track and put this under the track. Once this was
complete I filled in under the track with a dry mix of sand and
cement packing it in until the track was up to the height I
required. This is quite easy and allows plenty of time to think
about things and get it right. Once I was happy that all was
correct I put a wet mix along both sides of the dry mix and
everything stayed in place. This works for me but I know there
are many different methods available.

Eventually I got to the lower end
of the slope and achieved the required height at pretty much the
planned position. The only expenditure was on a few new points
so the whole project was remarkably cheap. The storage loops
have been laid out and trains are now running on a suitably
engineered main line. Maybe not in the same league as Brunel’s
main line but fine for my garden. The photo below shows the nice
smooth climb on the line in the background.

Chris
Morris
Spring
2007.
|